PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 12 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 12 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?


A.

Assess the risk register to ensure the secondary risks are realistic.


B.

Assess the impact of residual and secondary risks on project objectives.


C.

Assess the change log to establish that changes were implemented.


D.

Assess the stakeholder register to determine the impact of initial risks. 