PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 12 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 12 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?


A.

Risks are documented to the practicable extent possible.


B.

Probability of the risk was very low. so the risk was not documented.


C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.


D.

A similar risk never occurred in the past, so it was not considered. 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.