Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 13 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 13 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.

What should the risk manager do?


A.

Assume the vendor will deliver on time and focus only on internal risks.


B.

Allocate contingency funds without first evaluating the risk ' s probability and impact.


C.

Wait indefinitely for the vendor ' s update before analyzing the risk.


D.

Assess the risk using a probability-impact matrix and prioritize it based on its score.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.