PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 13 Topic 2 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 13 Topic 2 Discussion

PMI-RMP Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?


A.

Residual risk


B.

Primary risk


C.

Secondary risk


D.

Normal risk


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.