Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 4 out of 9 pages
Viewing questions 31-40 out of questions
Questions # 31:

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.


B.

Update the risk management plan to reflect the scope change.


C.

Reassess the identified risks that impact the project scope.


D.

Update the risk register to identify, analyze, and plan a response for any new risk.


Expert Solution
Questions # 32:

A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.


B.

Both options are losses to the project.


C.

Cost to expedite the execution is not worth the added risk.


D.

Perform a Monte Carlo simul-ation to quantify the impacts.


Expert Solution
Questions # 33:

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned


B.

Contingency register


C.

Risk register


D.

Issue log


Expert Solution
Questions # 34:

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Options:

A.

To enable the team in identifying the specific causes of risks associated with project objectives.


B.

To ensure that project priorities are being appropriately factored into risk response plans.


C.

To determine there more attentive project leadership and organizational involvement is needed.


D.

To assign risks and risk severities to functional discipline and departments effectively.


Expert Solution
Questions # 35:

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000


B.

US$52,000


C.

US$120,000


D.

US$80,000


Expert Solution
Questions # 36:

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

Options:

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.


B.

Refer to the project charter to find guidelines and stakeholder communication channels.


C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.


D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.


Expert Solution
Questions # 37:

A project manager is educating the project team on risk management regarding the role of threats and opportunities. The team decides to log the opportunities in the current project ' s risk register to try to maximize their chances of occurrence.

What should the project team do next?

Options:

A.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.


B.

Log the threats in the risk register to try to minimize the probability of occurrence.


C.

Log the threats in the risk register to try to maximize the probability of occurrence.


D.

Update the project management plan to ensure the results of the opportunities are captured.


Expert Solution
Questions # 38:

During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.

What should the risk manager do?

Options:

A.

Assign a risk owner and develop the risk mitigations at the next scheduled risk meeting.


B.

Continue with the project as the risk identified is inconsequential.


C.

Assign risk responsibility to the project manager to determine how to proceed.


D.

Update the project stakeholders and seek their input on the resulting secondary risk.


Expert Solution
Questions # 39:

in a complex and critical project, a sponsor asks the risk manager to determine where the project ' s concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Options:

A.

Work breakdown structure (WBS)


B.

Affinity diagram


C.

Monte Carlo simul-ation


D.

Mind mapping


Expert Solution
Questions # 40:

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.


B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.


C.

Assess and record associated secondary risks and proceed to treat them as any other risks.


D.

Proceed with the project as normal since a minor number of residents will be effected negatively.


Expert Solution
Viewing page 4 out of 9 pages
Viewing questions 31-40 out of questions