Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 4 out of 9 pages
Viewing questions 31-40 out of questions
Questions # 31:

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity


B.

Add more contingency to the project


C.

Review the plans for the key activity


D.

Increase the budget for the key activity


Expert Solution
Questions # 32:

A risk manager is working with a key project stakeholder who is concerned about the likelihood of quality issues such as product defects or process anomalies. The stakeholder has a low tolerance for any defects. The risk manager needs to tailor the risk management strategy to accommodate the stakeholder ' s risk appetite.

What should the risk manager do?

Options:

A.

Use Lean Six Sigma processes to ensure there are no defects.


B.

Request more funds in the risk reserve for defect management.


C.

Refine probability definitions to align with the stakeholder ' s risk tolerance.


D.

Conform to the stakeholder ' s risk tolerance levels by using Lean principles.


Expert Solution
Questions # 33:

A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.

What should the risk manager have done to prevent this situation?

Options:

A.

Engaged the sponsor and informed them of the decision to remove the planned feature.


B.

Engaged the stakeholders more in risk management activities and decisions to get their buy-in and support.


C.

Performed proper risk identification at the project outset to ensure this risk was identified and mitigated.


D.

Created a schedule buffer in the plan to deal with unknown risks if and when they occurred. 


Expert Solution
Questions # 34:

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project ' s technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

Options:

A.

Immediately hire as soon as the project begins to fall behind schedule.


B.

Hire as soon as the project metrics trigger a risk response.


C.

Only hire when it is economically feasible to do so.


D.

Only hire if risk response is escalated and approved by the stakeholders. 


Expert Solution
Questions # 35:

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization


B.

The risk simul-ation


C.

The full risk description


D.

The risk response plan


Expert Solution
Questions # 36:

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies


B.

Commercial risk databases


C.

Organizational process assets (OPAs)


D.

Enterprise environmental factors (EEFs)


Expert Solution
Questions # 37:

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Options:

A.

Risk mitigation


B.

Risk transfer


C.

Risk acceptance


D.

Risk avoidance


Expert Solution
Questions # 38:

A project manager has requested the risk manager ' s support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.


B.

Both options are losses to the project.


C.

Cost to expedite the execution is not worth the added risk.


D.

Perform a Monte Carlo simul-ation to quantify the impacts.


Expert Solution
Questions # 39:

As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.

What additional information should the risk manager prioritize in the risk register updates?

Options:

A.

Actual outcomes and performance of risk management strategies


B.

Actual outcomes of the project ' s risks and risk responses


C.

Actual costs and schedule delays of risk events


D.

Actual cost impact of risk events


Expert Solution
Questions # 40:

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager ' s next step?

Options:

A.

Check the schedule for constraints


B.

Use the P90 date on the risk report


C.

Decrease the number of iterations


D.

Decrease the risk consequences


Expert Solution
Viewing page 4 out of 9 pages
Viewing questions 31-40 out of questions