Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 8 out of 9 pages
Viewing questions 71-80 out of questions
Questions # 71:

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project ' s contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Options:

A.

Process the freight invoices at higher shipping costs against the project ' s contingency allowance.


B.

Request a formal change order from the customer to increase the project ' s total budget.


C.

Process the freight invoices for the budgeted amount and hope the shipping company will forgive the difference.


D.

Ask the project sponsor to cover the additional shipping costs on the company ' s reserves account.


Expert Solution
Questions # 72:

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project ' s total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Options:

A.

Activity 3.2


B.

Activity 2.3


C.

Activity 3.5


D.

Activity 1.2


Expert Solution
Questions # 73:

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?

Options:

A.

Follow up on the schedule and assess the best course of action if any delays are detected.


B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.


C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.


D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 


Expert Solution
Questions # 74:

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.


B.

Assess and modify the project risk management plan in response to the new directive.


C.

Accept project risks since it is already within the enterprise-wide threshold.


D.

Advise that the decision could increase the risk of their portfolio exponentially.


Expert Solution
Questions # 75:

A risk manager is assigned to a mobile network deployment project with a strict contractually agreed-on schedule. One of the key risks identified has materialized. There is insufficient staffing because critical resources are dedicated to strategic projects in the organization. The risk manager expected the resource manager to notice this, but the resource manager thought the project experts would be alerting the team during the project.

What should the risk manager do to prevent this from happening again?

Options:

A.

Document the risks and response actions in a clear manner.


B.

Communicate with the project manager on the topic.


C.

Assign owners who will be fully accountable to managing the risks.


D.

Define the response plans and take the lead in implementing them.


Expert Solution
Questions # 76:

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

Options:

A.

Probability tree diagram


B.

Ishikawa diagram


C.

Decision tree analysis


D.

Monte Carlo simul-ation


Expert Solution
Questions # 77:

A project manager was informed that the testing of the latest component in the project ' s software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Options:

A.

Add contingencies to other tasks to mitigate similar risks.


B.

Reassess risks with a new assumptions and constraints analysis.


C.

Review the risk response plan looking for lessons learned.


D.

Log the event in the issue log and update the project management plan.


Expert Solution
Questions # 78:

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned


B.

Contingency register


C.

Risk register


D.

Issue log


Expert Solution
Questions # 79:

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information


B.

Conduct interviews, meetings, and focus groups


C.

Assign a different risk manager for each portfolio unit


D.

Employ brainstorming to generate spontaneous ideas


E.

Perform qualitative and quantitative risk analyses 


Expert Solution
Questions # 80:

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.

Use the information for a risk workshop.


B.

Improve monitoring and controlling of activities.


C.

Document the issues in the lessons learned.


D.

Create an issue log to share with the team.


Expert Solution
Viewing page 8 out of 9 pages
Viewing questions 71-80 out of questions