Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 8 out of 9 pages
Viewing questions 71-80 out of questions
Questions # 71:

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project ' s risk management plan.


B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses


C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.


D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 


Expert Solution
Questions # 72:

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.


B.

Inform the sponsor that these risks should be added according to experience.


C.

Add the risks to the risk register and determine a contingency.


D.

Discuss and evaluate the identified risks with the project team.


Expert Solution
Questions # 73:

A software company has recently completed a project that delivered a new web application. Throughout the project, several issues were realized that resulted in cost and schedule overruns. The project ' s executive sponsor has requested a deep-dive into what went wrong since the company will be developing additional web applications in the future.

What should the risk manager do?

Options:

A.

Gather the project ' s status reports and meeting minutes to determine when issues occurred and how quickly the issues were addressed.


B.

Conduct a retrospective meeting with stakeholders and inquire about what went well and what could be improved on future projects.


C.

Work with the project manager to determine if additional resources could have prevented or mitigated the issues that arose on the project.


D.

Review the project ' s risk register and determine how comprehensive and effective each risk and issue response was.


Expert Solution
Questions # 74:

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Options:

A.

Accept actively


B.

Mitigate


C.

Accept passively


D.

Share


Expert Solution
Questions # 75:

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.

Product Manager


B.

Risk Action Owner


C.

Risk Owner


D.

Project Manager


Expert Solution
Questions # 76:

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis


B.

Residual impact analysis


C.

Sensitivity analysis


D.

Reserve analysis 


Expert Solution
Questions # 77:

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization ' s risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.


B.

Conduct meeting with all stakeholder to agree on post impact solutions.


C.

Set the corresponding trigger conditions to the secondary risk.


D.

Engage the project manager to authorize the secondary risk ' s response.


E.

Update and communicate assessments of the secondary risk ' s impact.


Expert Solution
Questions # 78:

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.

Schedule and resource assumptions


B.

Contingency reserves


C.

Work breakdown structure (WBS)


D.

Risk impact matrix


Expert Solution
Questions # 79:

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

Options:

A.

The audit team


B.

The risk manager


C.

The risk owners


D.

The discipline engineers


Expert Solution
Questions # 80:

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.


B.

Advise the client that the project has exhausted contingency.


C.

Quantify the risk exposure that exceeds project contingency.


D.

Generate reports to assess and communicate the project risk level.


Expert Solution
Viewing page 8 out of 9 pages
Viewing questions 71-80 out of questions