Questions # 81:

A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.

What should the risk manager do?

Options:

A.

Focus on high-probability concerns first to proactively address the most immediate threats.


B.

Delegate the assessment of lower-priority concerns to team leads while addressing critical ones.


C.

Evaluate all identified concerns and consider likelihood and impact to prioritize the concerns effectively.


D.

Prioritize uncertainties that align closely with the project ' s primary deliverables.


Expert Solution
Questions # 82:

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?

Options:

A.

Update the risk register accordingly and review it in regular project meetings.


B.

Accept the risk because residual risks are often low.


C.

Ask a subject matter expert (SME) to assess the residual risk and take action.


D.

Assign a risk owner and set it as high priority and high impact.


Expert Solution
Questions # 83:

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind


B.

Review the results with the project manager afterward


C.

Review published operational experience reports


D.

Use the mean answers provided by the project team 


Expert Solution