Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 82 Topic 9 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 82 Topic 9 Discussion

PMI-RMP Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.

What should the risk manager do?


A.

Update the risk register accordingly and review it in regular project meetings.


B.

Accept the risk because residual risks are often low.


C.

Ask a subject matter expert (SME) to assess the residual risk and take action.


D.

Assign a risk owner and set it as high priority and high impact.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.