Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 7 out of 9 pages
Viewing questions 61-70 out of questions
Questions # 61:

A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

Options:

A.

Sensitivity analysis


B.

Qualitative analysis


C.

Statistical analysis


D.

Impact analysis 


Expert Solution
Questions # 62:

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.

Utilize a Monte Carlo assessment to provide risk related impacts.


B.

React to the secondary and residual risks only if they occur.


C.

Include secondary and residual risks as part of the response.


D.

Transfer secondary and residual risks to the project sponsor.


Expert Solution
Questions # 63:

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.


B.

Ask the project sponsor to approve shipping the equipment.


C.

Proceed with the planned risk response to move the equipment.


D.

Request the shipment of the equipment to satisfy the client.


Expert Solution
Questions # 64:

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?

Options:

A.

Detailed work breakdown structure (WBS)


B.

Lessons learned from previous projects


C.

Baselines approved by the project team


D.

Actual data from the current project


Expert Solution
Questions # 65:

A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project ' s timeline. The project team is struggling to finalize the project ' s budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project ' s final cost. The project team will not be able to finalize the project ' s timeline until the budget is finalized.

What should the risk manager do?

Options:

A.

Request an extension to mitigate schedule constraints.


B.

Register the risks as vendor issues and avoid further action.


C.

Log the risk and the response strategies in the risk register.


D.

Catalog the risks as assumptions and avoid further action.


Expert Solution
Questions # 66:

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.

Review the agreed-upon risk tolerance


B.

Perform a sensitivity analysis of the risk


C.

Find out the stakeholders’ risk appetite


D.

Use industry standard risk thresholds


Expert Solution
Questions # 67:

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project ' s budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

Options:

A.

Stakeholder management and communication tools


B.

Team performance reports and analysis tools


C.

Schedule management tools (i.e., Gantt Charts)


D.

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations) 


Expert Solution
Questions # 68:

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Options:

A.

Escalate the problem to the project sponsors.


B.

Execute the approved risk response plan.


C.

Negotiate with the supplier to resolve the problem.


D.

Assign a team member to update the issue leg.


Expert Solution
Questions # 69:

A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.

What process is this part of?

Options:

A.

Plan Risk Management


B.

Perform Qualitative Risk Analysis


C.

Perform Quantitative Risk Analysis


D.

Monitor and Control Risk


Expert Solution
Questions # 70:

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.

Add buffers to the schedule to accommodate risk.


B.

Ensure the risk register includes all identified risks.


C.

Discuss the risk response strategies with the stakeholders.


D.

Develop a communication plan to share updates on risks.


Expert Solution
Viewing page 7 out of 9 pages
Viewing questions 61-70 out of questions