Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 7 out of 9 pages
Viewing questions 61-70 out of questions
Questions # 61:

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.


B.

Activate the contingency plan to handle this risk during execution.


C.

Mark this new risk as an extremely high priority and inform all stakeholders.


D.

Ask the project sponsor for more budget to deal with this risk.


Expert Solution
Questions # 62:

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

Options:

A.

US$20.000 loss


B.

US$20,000 profit


C.

US$40,000 loss


D.

US$100,000 profit


Expert Solution
Questions # 63:

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

Options:

A.

Agree with the external supplier on the timeline.


B.

Register the risk with a medium impact.


C.

Align with stakeholders on the risk threshold.


D.

Engage another supplier with shorter delivery times.


Expert Solution
Questions # 64:

A technology company is in the final stages of an IT system implementation project. As part of ongoing risk monitoring, the risk manager reviews current risk levels and identifies significant changes in the external regulatory environment that may affect project delivery.

What should the risk manager do next?

Options:

A.

Engage the operations team to assess the environment for issues.


B.

Request that the project management office add resources to address these risks.


C.

Expedite project completion to avoid potential impacts from the new risks.


D.

Work with the project team to reassess the environment for new risks.


Expert Solution
Questions # 65:

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Options:

A.

Execute the security risks contingency plan.


B.

Get a report of customers affected by the risk.


C.

Identify residual and secondary risks.


D.

Coordinate a response with the risk owner.


Expert Solution
Questions # 66:

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

Options:

A.

The audit team


B.

The risk manager


C.

The risk owners


D.

The discipline engineers


Expert Solution
Questions # 67:

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.

Ensuring that the project sponsor is kept well-informed


B.

Arranging periodic risk: management process audits


C.

Communicating the status of risks regularly to stakeholders


D.

Monitoring costs with intervention when necessary


Expert Solution
Questions # 68:

In reviewing the team ' s identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project ' s incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Options:

A.

Exploit


B.

Accept


C.

Share


D.

Enhance 


Expert Solution
Questions # 69:

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.


B.

The cost baseline is inaccurate.


C.

The actual reported costs are inaccurate.


D.

The cost related risks are effectively managed.


Expert Solution
Questions # 70:

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.


B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.


C.

Assess and record associated secondary risks and proceed to treat them as any other risks.


D.

Proceed with the project as normal since a minor number of residents will be effected negatively.


Expert Solution
Viewing page 7 out of 9 pages
Viewing questions 61-70 out of questions