PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 66 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 66 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)


A.

By helping to monitor variances and trends frequently throughout the project


B.

By helping to determine the overall project risks


C.

By helping the lessons learned from previous risks to be efficiently utilized


D.

By helping to update the project scope statement document


E.

By helping update the risk register and close out expired risks 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.