Question #: 66
Topic #: 7

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?


A.

Review the agreed-upon risk tolerance


B.

Perform a sensitivity analysis of the risk


C.

Find out the stakeholders’ risk appetite


D.

Use industry standard risk thresholds