PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 68 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 68 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 68 Discussion:
Question #: 68
Topic #: 7

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?


A.

Revisit this risk in the risk register and redefine the mitigation strategy.


B.

Activate the contingency plan to handle this risk during execution.


C.

Mark this new risk as an extremely high priority and inform all stakeholders.


D.

Ask the project sponsor for more budget to deal with this risk.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.