Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 67 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 67 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project ' s budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?


A.

Stakeholder management and communication tools


B.

Team performance reports and analysis tools


C.

Schedule management tools (i.e., Gantt Charts)


D.

Estimation and probability analysis tools (i.e. Monte Carlo simul-ations) 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.