PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 61 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 61 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?


A.

Create a new project plan including the new risks.


B.

Review the effectiveness of the risk process.


C.

Update the risk management plan.


D.

Escalate the project risks to upper management. 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.