PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 60 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 60 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)


A.

Verify whether or not any identified risks might occur and implement the risk response plan.


B.

Regularly check and report on the status of risks identified according to their prioritization.


C.

Monitor the status and oversee execution of the risk response plan for each identified risk.


D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.


E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.