Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 3 out of 9 pages
Viewing questions 21-30 out of questions
Questions # 21:

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

Options:

A.

Perform a probability and impact assessment


B.

Perform Monte Carlo simul-ations


C.

Perform a sensitivity analysis


D.

Perform a risk data quality assessment


Expert Solution
Questions # 22:

What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

Options:

A.

Organizational communication requirements


B.

Organizational standard policies, processes, and procedures


C.

Formal knowledge sharing and information sharing procedures


D.

Confidentiality of project information


Expert Solution
Questions # 23:

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

Options:

A.

Perform time recovery actions.


B.

Execute the prevention plans.


C.

Execute the contingency plans.


D.

Perform change management.


Expert Solution
Questions # 24:

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project ' s complexity, what should the risk manager do?

Options:

A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.


B.

Conduct the exercise with the key team members, excluding external stakeholders.


C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.


D.

Focus only on identifying the most obvious risks to save time and project resources.


Expert Solution
Questions # 25:

A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Options:

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.


B.

The ideal solution is to find alternate documents that provide good visibility on the environment.


C.

The risk identification process can be carried out as long as the project statement is available.


D.

Risk evaluation will be challenging without these elements as a frame of reference.


Expert Solution
Questions # 26:

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.

Which technique should the risk manager use in this situation?

Options:

A.

Brainstorming


B.

Delphi method


C.

Focus group


D.

Checklist analysis


Expert Solution
Questions # 27:

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Options:

A.

Request for a skilled facilitator to help resolve conflicts that have arise.


B.

Refer to the team’s ground rules on how to resolve conflicts.


C.

Run a sensitivity analysis to check which risks have the most impact.


D.

Use the assumption analysis techniques to validate the assumptions.


Expert Solution
Questions # 28:

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Options:

A.

Close the risks and update their status in the risk register.


B.

Use their contingency with other risks that are still open.


C.

Remove the risk from the list as they are no longer applicable.


D.

Reevaluate those risks ' severity, and update the risk register.


Expert Solution
Questions # 29:

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost


B.

Communicated with the stakeholders that the project costs might increase


C.

Properly documented the triggers and actions for the risk


D.

Engaged with the sponsor to buy the steel in advance of the project 


Expert Solution
Questions # 30:

A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.

What should the risk manager advise the team to do first?

Options:

A.

Mitigate the risk by asking the team member to gather more information.


B.

Add the risk to the issue log and revisit it when there is more information.


C.

Arrange a meeting with the stakeholder to discuss the risk and information.


D.

Add the risk to the risk register and gather information about its probability and impact. 


Expert Solution
Viewing page 3 out of 9 pages
Viewing questions 21-30 out of questions