PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 30 Topic 4 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 30 Topic 4 Discussion

PMI-RMP Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

A new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?


A.

Detailed work breakdown structure (WBS)


B.

Lessons learned from previous projects


C.

Baselines approved by the project team


D.

Actual data from the current project


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.