PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 27 Topic 3 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 27 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers

this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about

to drop their intention to continue executing the project. The risk manager does not understand their decision.

What should the risk manager do next to understand the major stakeholder's decision regarding the project?


A.

Perform a risk impact analysis.


B.

Perform a risk reserve analysis.


C.

Perform a procurement analysis.


D.

Perform a stakeholder impact and influence analysis.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.