Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 27 Topic 3 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 27 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?


A.

Request for a skilled facilitator to help resolve conflicts that have arise.


B.

Refer to the team’s ground rules on how to resolve conflicts.


C.

Run a sensitivity analysis to check which risks have the most impact.


D.

Use the assumption analysis techniques to validate the assumptions.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.