Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 25 Topic 3 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 25 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

A project team has just initiated a large project to move an organization ' s headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?


A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.


B.

The ideal solution is to find alternate documents that provide good visibility on the environment.


C.

The risk identification process can be carried out as long as the project statement is available.


D.

Risk evaluation will be challenging without these elements as a frame of reference.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.