PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 23 Topic 3 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 23 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?


A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.


B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.


C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.


D.

Add the identified risk to the risk register for future probability and impact analysis.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.