Question #: 22
Topic #: 3

A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization's project risk baseline.

What should the risk manager do?


A.

Prioritize the risk management plan.


B.

Arrange the risk mitigation plan.


C.

Create a risk action plan with risk owners.


D.

Prioritize the risk register.