PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 24 Topic 3 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 24 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?


A.

Product Manager


B.

Risk Action Owner


C.

Risk Owner


D.

Project Manager


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.