PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 24 Topic 3 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 24 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project ' s complexity, what should the risk manager do?


A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.


B.

Conduct the exercise with the key team members, excluding external stakeholders.


C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.


D.

Focus only on identifying the most obvious risks to save time and project resources.