Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 6 out of 9 pages
Viewing questions 51-60 out of questions
Questions # 51:

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option ' s success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis


B.

Conduct a sensitivity analysis


C.

Perform a decision tree analysis


D.

Conduct an analytic hierarchy process


Expert Solution
Questions # 52:

A key hardware component failed during a large software implementation project, with significant organizational impact. The risk owner was on vacation and no one responded to this incident, thereby causing project delays.

What should have been done to prevent this situation?

Options:

A.

The project manager should have requested and mandated that no vacations be taken during critical implementation activities or until all implementation had been completed for the project.


B.

The risk manager should have anticipated this situation and planned for schedule buffers in the project schedule to accommodate the likelihood of failed hardware.


C.

The risk owner should have communicated with the project manager so that a designated stakeholder could have been assigned to accept accountability for implementing risk responses.


D.

The risk manager should have taken the responsibility of responding to this risk instead of relying on and waiting for the risk owner to return from vacation.


Expert Solution
Questions # 53:

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

Options:

A.

Prepare a contingency response plan to implement when delays occur


B.

Ask the other project manager to officially confirm the new date in writing


C.

Request that the other project manager be added to relevant reports


D.

Request that the other project manager inform if any additional delays are expected


Expert Solution
Questions # 54:

A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.

What should the risk manager do next?

Options:

A.

Update the work breakdown structure (WBS).


B.

Analyze any potential impact.


C.

Escalate the issue to management.


D.

Add a new risk to the risk register.


Expert Solution
Questions # 55:

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?

Options:

A.

Ensured to include the stakeholders in the team discussions


B.

Encouraged involvement of the project team during the review meetings


C.

Enhanced communication with the sponsor regarding secondary risk impact


D.

Ensured the sponsor got more involved with the project risk planning


Expert Solution
Questions # 56:

A key project is delayed and all contingency reserves have been used even though the project team has implemented all planned risk responses. What should the risk manager do next?

Options:

A.

Create a new project plan including the new risks.


B.

Review the effectiveness of the risk process.


C.

Update the risk management plan.


D.

Escalate the project risks to upper management. 


Expert Solution
Questions # 57:

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.

Update the new risk in the risk register.


B.

Plan responses for the new risk.


C.

Passively accept the new risk.


D.

Add the new risk to the watch list.


Expert Solution
Questions # 58:

During the execution phase of a construction project, a risk response strategy is implemented to mitigate the risk of supply chain disruptions. However, this leads to a secondary risk of increased logistics costs.

What should the risk manager do to address the new risk of increased logistics costs?

Options:

A.

Accept the increased costs as part of the project ' s risk threshold.


B.

Develop a contingency plan to cover additional logistics expenses.


C.

Switch suppliers to potentially reduce logistics expenses.


D.

Incorporate a cost-sharing arrangement with the suppliers.


Expert Solution
Questions # 59:

A risk manager has been assigned to replace a risk manager on sick leave. The new risk manager notices that the risk register is missing data that are key to the risk management process.

Which data will the risk manager require first?

Options:

A.

Risk description risk response, and quantitative data


B.

Project plan, risk complexity, and secondary risk


C.

Project plan, risk priority, and tool availability


D.

Risk description, risk probability, and risk impact 


Expert Solution
Questions # 60:

A nonprofit organization is working on a project to deliver a fundraising concert event. The concert is only a few weeks away, and the project team has completed revising the risk processes when an opportunity is identified. The key stakeholders want to capitalize on it.

What should the risk manager do?

Options:

A.

Accept the opportunity and look for options to mitigate it.


B.

Direct the team to explore the likelihood of enhancing the opportunity.


C.

Work with the team to identify a suitable owner for the opportunity.


D.

Continue to monitor and document the opportunity.


Expert Solution
Viewing page 6 out of 9 pages
Viewing questions 51-60 out of questions