Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 6 out of 9 pages
Viewing questions 51-60 out of questions
Questions # 51:

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies


B.

Commercial risk databases


C.

Organizational process assets (OPAs)


D.

Enterprise environmental factors (EEFs)


Expert Solution
Questions # 52:

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.


B.

Escalate the situation and request approval to move forward.


C.

Confirm the results through a second pilot.


D.

Update the assumptions log and assess the risk associated with it.


Expert Solution
Questions # 53:

A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)

Options:

A.

Applying modern risk management techniques.


B.

Aligning to project constraints and priorities.


C.

Ensuring risk response strategies mitigate all risks.


D.

Minimizing implementation costs.


E.

Obtaining stakeholder acceptance


Expert Solution
Questions # 54:

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.


B.

Determine the workarounds for the program risks and allocate responsibilities to the team.


C.

Allow the most experienced program manager to handle the most critical program risks.


D.

Encourage the program team to assume risk ownership prior to delegation. 


Expert Solution
Questions # 55:

A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.

How should the risk manager explain the need for a risk strategy specific to this project?

Options:

A.

A risk strategy is a best practice and ensures quality in the project planning.


B.

A project specific risk strategy includes enough information to respond to audits and compliance requirements.


C.

A risk strategy ensures alignment of the organizational structure to the specific project.


D.

A risk strategy aligns individual project risk thresholds with organizational risk appetite. 


Expert Solution
Questions # 56:

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram


B.

Perform the analytical hierarchy process


C.

Perform a SWOT analysis


D.

Assign probability and impact


Expert Solution
Questions # 57:

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.


B.

Update the assumptions/exclusions register with the new information.


C.

Update the risk register and prepare for the Monte Carlo analysis.


D.

Perform a quantitative risk analysis and update the results.


Expert Solution
Questions # 58:

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.


B.

Change the response strategies.


C.

Reduce the contingency reserves.


D.

Conduct a risk planning workshop.


Expert Solution
Questions # 59:

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.

Use the information for a risk workshop.


B.

Improve monitoring and controlling of activities.


C.

Document the issues in the lessons learned.


D.

Create an issue log to share with the team.


Expert Solution
Questions # 60:

A project team ' s manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).

How many total story points is the entire initiative?

Options:

A.

72


B.

60


C.

40


D.

32


Expert Solution
Viewing page 6 out of 9 pages
Viewing questions 51-60 out of questions