PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 53 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 53 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?


A.

Close the risks and update their status in the risk register.


B.

Use their contingency with other risks that are still open.


C.

Remove the risk from the list as they are no longer applicable.


D.

Reevaluate those risks' severity, and update the risk register.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.