Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 52 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 52 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?


A.

Reassess the design for the two pieces.


B.

Escalate the situation and request approval to move forward.


C.

Confirm the results through a second pilot.


D.

Update the assumptions log and assess the risk associated with it.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.