A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option ' s success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?


A.

Perform a FMECA fault tree analysis


B.

Conduct a sensitivity analysis


C.

Perform a decision tree analysis


D.

Conduct an analytic hierarchy process