Question #: 50
Topic #: 6

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?


A.

The risk categorization


B.

The risk simul-ation


C.

The full risk description


D.

The risk response plan