PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 56 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 56 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?


A.

Conduct a subject matter expert (SME) meeting.


B.

Perform qualitative analysis.


C.

Prioritize after quantitative analysis


D.

Prioritize the stakeholders affected.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.