PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 54 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 54 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 54 Discussion:
Question #: 54
Topic #: 6

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?


A.

Updated probability and impact matrix


B.

Updated risk register


C.

Updated mitigation plans


D.

Updated project schedule 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.