Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 54 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 54 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 54 Discussion:
Question #: 54
Topic #: 6

A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.

What should the risk manager do next?


A.

Update the work breakdown structure (WBS).


B.

Analyze any potential impact.


C.

Escalate the issue to management.


D.

Add a new risk to the risk register.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.