PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 54 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 54 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 54 Discussion:
Question #: 54
Topic #: 6

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?


A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.


B.

Determine the workarounds for the program risks and allocate responsibilities to the team.


C.

Allow the most experienced program manager to handle the most critical program risks.


D.

Encourage the program team to assume risk ownership prior to delegation. 