PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 58 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 58 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 58 Discussion:
Question #: 58
Topic #: 6

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?


A.

Time Series Analysis


B.

Regression Analysis


C.

Variance Analysis


D.

Monte Carlo Analysis 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.