PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 58 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 58 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 58 Discussion:
Question #: 58
Topic #: 6

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?


A.

Review project schedule estimates.


B.

Change the response strategies.


C.

Reduce the contingency reserves.


D.

Conduct a risk planning workshop.