Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 59 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 59 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?


A.

Use the information for a risk workshop.


B.

Improve monitoring and controlling of activities.


C.

Document the issues in the lessons learned.


D.

Create an issue log to share with the team.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.