PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 59 Topic 6 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 59 Topic 6 Discussion

PMI-RMP Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?


A.

Probability of a response triggering a secondary risk


B.

How the response will affect the quality of the components


C.

If the risk response is tied to an activity on the critical path


D.

Verify due dates for the actions have been identified


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.