Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 2 out of 9 pages
Viewing questions 11-20 out of questions
Questions # 11:

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.


B.

Develop risk response plans for all identified risks.


C.

Update the communications management plan to avoid future issues


D.

Monitor and control secondary and residual risks in the risk register.


Expert Solution
Questions # 12:

During project development, a risk manager notices that a major update in the country ' s regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.

Which tool should the project team use to determine this?

Options:

A.

Sensitivity analysis


B.

Threshold analysis


C.

Reserve analysis


D.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis 


Expert Solution
Questions # 13:

During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.

What should the risk manager do?

Options:

A.

Assume the vendor will deliver on time and focus only on internal risks.


B.

Allocate contingency funds without first evaluating the risk ' s probability and impact.


C.

Wait indefinitely for the vendor ' s update before analyzing the risk.


D.

Assess the risk using a probability-impact matrix and prioritize it based on its score.


Expert Solution
Questions # 14:

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact.

Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options:

A.

Work with the project team to conduct a decision tree analysis for each risk or set of related risks.


B.

Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and defend project reserves.


C.

Conduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.


D.

Use the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure project reserves are adequate to cover this amount.


E.

Focus attention and resources on identified risks with the highest potential to impact the project.


Expert Solution
Questions # 15:

A major data center initiative involves performing a sensitivity analysis to determine the center ' s required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor ' s advertised plans.

What should the risk manager do to quantify the risk?

Options:

A.

Initiate a 360-degree assessment.


B.

Consult environmental enterprise factors for benchmarks.


C.

Review organizational process assets for guidance.


D.

Consider leveraging the Delphi technique.


Expert Solution
Questions # 16:

What should the risk owner use as an effective information-gathering technique during the planning session?

Options:

A.

Monte Carlo analysis


B.

Update risk register


C.

Brainstorming


D.

Cost and time estimating


Expert Solution
Questions # 17:

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

Options:

A.

Include the risk in the register and communicate with the stakeholders.


B.

Communicate with the client to provide the previous shutdown plan.


C.

Review and update the project schedule.


D.

Interview the other project manager to learn more details.


Expert Solution
Questions # 18:

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.

Release this version and leave changes to be done at the end of the project phase.


B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.


C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.


D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.


Expert Solution
Questions # 19:

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?

Options:

A.

Check list analysis


B.

Cause and effect


C.

Specialized meeting


D.

Quantitative analysis


Expert Solution
Questions # 20:

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project ' s risk management activities? (Choose 3)

Options:

A.

By helping to monitor variances and trends frequently throughout the project


B.

By helping to determine the overall project risks


C.

By helping the lessons learned from previous risks to be efficiently utilized


D.

By helping to update the project scope statement document


E.

By helping update the risk register and close out expired risks 


Expert Solution
Viewing page 2 out of 9 pages
Viewing questions 11-20 out of questions