Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

Pass the PMI PMI Certification PMI-RMP Questions and answers with CertsForce

Viewing page 2 out of 9 pages
Viewing questions 11-20 out of questions
Questions # 11:

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.


B.

Inform the sponsor that these risks should be added according to experience.


C.

Add the risks to the risk register and determine a contingency.


D.

Discuss and evaluate the identified risks with the project team.


Expert Solution
Questions # 12:

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

Options:

A.

Assess the risk register to ensure the secondary risks are realistic.


B.

Assess the impact of residual and secondary risks on project objectives.


C.

Assess the change log to establish that changes were implemented.


D.

Assess the stakeholder register to determine the impact of initial risks. 


Expert Solution
Questions # 13:

During a project ' s initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk ' s likelihood and impact with the risk manager.

What should the risk manager do?

Options:

A.

Assume the vendor will deliver on time and focus only on internal risks.


B.

Allocate contingency funds without first evaluating the risk ' s probability and impact.


C.

Wait indefinitely for the vendor ' s update before analyzing the risk.


D.

Assess the risk using a probability-impact matrix and prioritize it based on its score.


Expert Solution
Questions # 14:

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?

Options:

A.

Prioritize opportunities as they are likely to bring benefits to the project.


B.

Analyze the risks and add them to the risk register to continue the process.


C.

Create a separate project to exclusively manage positive risks and threats.


D.

Assign separate stakeholder groups for positive risks and negative risks.


Expert Solution
Questions # 15:

A risk manager is overseeing the construction of a new office building and finds that some risks were underestimated in their impact on the project timeline and budget. The risk manager is reassessing the current risk levels to prevent further escalation.

Which two actions should the risk manager take? Choose two.

Options:

A.

Conduct a detailed risk audit to verify the accuracy of the risk assessments.


B.

Implement automation to track project risks in real time.


C.

Adjust risk priorities in the risk register based on the new assessment data.


D.

Facilitate a risk-planning workshop to select strategies for the high-priority risks.


E.

Reassess risk exposure using predictive analytics tools.


Expert Solution
Questions # 16:

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Options:

A.

Adopt a predictive approach to manage the risks.


B.

Adopt agile approaches to manage the risks.


C.

Utilize proper documentation to help manage the risks.


D.

Conduct weekly risk management meetings with all stakeholders.


Expert Solution
Questions # 17:

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

Options:

A.

Review the stakeholders ' risk appetite.


B.

Revisit the risk thresholds and triggers.


C.

Update the risk response strategies.


D.

Provide coaching to the risk action owners. 


Expert Solution
Questions # 18:

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry ' s standard procedures


B.

Current request for proposal (RFP)


C.

Company ' s historical financial reports


D.

IT infrastructure, networks, and data information


E.

Government laws and regulations 


Expert Solution
Questions # 19:

A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

Options:

A.

Sensitivity analysis


B.

Qualitative analysis


C.

Statistical analysis


D.

Impact analysis 


Expert Solution
Questions # 20:

A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.

What should the risk manager do?

Options:

A.

Increase the residual risk monitoring.


B.

Increase the inherent risk monitoring.


C.

Reassess the inherent risk level.


D.

Reassess the residual risk level.


Expert Solution
Viewing page 2 out of 9 pages
Viewing questions 11-20 out of questions