During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?


A.

A potential need to share the space with other machinery


B.

A different type of equipment received before installation


C.

A time delay during air conditioning installation activities


D.

A quality nonconformance issue raised during the inspection