Question #: 35
Topic #: 4

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?


A.

US$68,000


B.

US$52,000


C.

US$120,000


D.

US$80,000