PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 44 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 44 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.

What should the project manager have done to avoid this?


A.

Provided regular training to the risk owners for plan implementation


B.

Determined risk triggers and thresholds in the risk response plan


C.

Increased communications to influence stakeholder risk responses


D.

Updated the project schedule, adding risk owner implementation tasks.