A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?


A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.


B.

Refer to the project charter to find guidelines and stakeholder communication channels.


C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.


D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.