Question #: 14
Topic #: 2

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?


A.

Perform a FMECA fault tree analysis


B.

Conduct a sensitivity analysis


C.

Perform a decision tree analysis


D.

Conduct an analytic hierarchy process