PMI-RMP Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?


A.

Prioritize opportunities as they are likely to bring benefits to the project.


B.

Analyze the risks and add them to the risk register to continue the process.


C.

Create a separate project to exclusively manage positive risks and threats.


D.

Assign separate stakeholder groups for positive risks and negative risks.