PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 63 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 63 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?


A.

When the forecast activity date has been met or exceeded


B.

When the stakeholders agree a risk is no longer applicable


C.

When the risk has been realized and can no longer happen again


D.

When iterative data analysis determines the risk is not applicable


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.