Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 63 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 63 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?


A.

Wait until the weather improves before sending the equipment.


B.

Ask the project sponsor to approve shipping the equipment.


C.

Proceed with the planned risk response to move the equipment.


D.

Request the shipment of the equipment to satisfy the client.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.