PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 64 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 64 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

A technology company is in the final stages of an IT system implementation project. As part of ongoing risk monitoring, the risk manager reviews current risk levels and identifies significant changes in the external regulatory environment that may affect project delivery.

What should the risk manager do next?


A.

Engage the operations team to assess the environment for issues.


B.

Request that the project management office add resources to address these risks.


C.

Expedite project completion to avoid potential impacts from the new risks.


D.

Work with the project team to reassess the environment for new risks.