PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 64 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 64 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?


A.

Carry out the agreed risk response action should the risk occur.


B.

Provide a numerical estimate of the overall effect of risk on the objectives.


C.

Track identified risks and maintain the viability of response plans.


D.

Develop the overall risk management strategy for risk integration. 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.