New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 65 Topic 7 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 65 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

A risk manager is preparing the risk strategy for a strategic project, which involves stakeholders based in multiple locations. What should the risk manager do at this stage?


A.

Update the risk communications plan to include all stakeholders.


B.

Define the risk processes and tools to be adopted.


C.

Update the risk register to include this stakeholder-related risk.


D.

Refine the risk assumptions and criteria to be used.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.