PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 78 Topic 8 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 78 Topic 8 Discussion

PMI-RMP Exam Topic 8 Question 78 Discussion:
Question #: 78
Topic #: 8

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?


A.

Schedule and resource assumptions


B.

Contingency reserves


C.

Work breakdown structure (WBS)


D.

Risk impact matrix