Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 79 Topic 8 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 79 Topic 8 Discussion

PMI-RMP Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?


A.

The audit team


B.

The risk manager


C.

The risk owners


D.

The discipline engineers


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.