Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 76 Topic 8 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 76 Topic 8 Discussion

PMI-RMP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?


A.

Probability tree diagram


B.

Ishikawa diagram


C.

Decision tree analysis


D.

Monte Carlo simul-ation


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.