PMI-RMP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?


A.

Variance analysis


B.

Residual impact analysis


C.

Sensitivity analysis


D.

Reserve analysis 