Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 73 Topic 8 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 73 Topic 8 Discussion

PMI-RMP Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

The scope of a large mobile network deployment project includes equipment to be furnished by the customer. The risk manager is concerned that the equipment delivery might be delayed, causing additional delays in the project.

What should the risk manager do?


A.

Follow up on the schedule and assess the best course of action if any delays are detected.


B.

Ensure the equipment constraint is well-documented and manage it as a high-impact project risk.


C.

Raise the issue with the project sponsor so it can be handled as a sales or contractual matter.


D.

Obtain a signed commitment from the customer that equipment will be delivered on time. 


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.