Question #: 33
Topic #: 4

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?


A.

Evaluating the project's probability of success


B.

Identifying threats and opportunities


C.

Evaluating the project's impact


D.

Performing a qualitative analysis