Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 32 Topic 4 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 32 Topic 4 Discussion

PMI-RMP Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

A risk manager is working with a key project stakeholder who is concerned about the likelihood of quality issues such as product defects or process anomalies. The stakeholder has a low tolerance for any defects. The risk manager needs to tailor the risk management strategy to accommodate the stakeholder ' s risk appetite.

What should the risk manager do?


A.

Use Lean Six Sigma processes to ensure there are no defects.


B.

Request more funds in the risk reserve for defect management.


C.

Refine probability definitions to align with the stakeholder ' s risk tolerance.


D.

Conform to the stakeholder ' s risk tolerance levels by using Lean principles.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.