PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 40 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 40 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager ' s next step?


A.

Check the schedule for constraints


B.

Use the P90 date on the risk report


C.

Decrease the number of iterations


D.

Decrease the risk consequences


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer: