PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 40 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 40 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?


A.

Engage with the team to present the actual results to the sponsor.


B.

Prepare a management of change (MOC) to adjust the project cost and duration.


C.

Move forward with the lessons learned from the sprint.


D.

Review the assumptions to understand any change.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.