PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 42 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 42 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?


A.

Perform a probability and impact assessment


B.

Perform Monte Carlo simul-ations


C.

Perform a sensitivity analysis


D.

Perform a risk data quality assessment


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.