PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 45 Topic 5 Discussion

PMI Risk Management Professional (PMI-RMP) Exam PMI-RMP Question # 45 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?


A.

Agree with the external supplier on the timeline.


B.

Register the risk with a medium impact.


C.

Align with stakeholders on the risk threshold.


D.

Engage another supplier with shorter delivery times.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.