Questions # 31:

NO: 98

The activity with the most total float is:

Question # 31

Options:

A.

Activity I.


B.

Activity C.


C.

Activity F.


D.

Activity D.


Expert Solution
Questions # 32:

During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

Options:

A.

Expedite Draft Product Manual by 5 days


B.

Delay Release for Manufacture by 5 days


C.

Delay Manufacture Product by 5 days


D.

Expedite Package Product by 5 days


Expert Solution
Questions # 33:

Each of the following accurately describes total float in a schedule EXCEPT:

Options:

A.

The amount of time an activity can be delayed without delaying the overall project completion time.


B.

Can be positive or negative.


C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.


D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.


Expert Solution
Questions # 34:

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Question # 34

Options:

A.

1001, 2001, 2002, 2003


B.

2001, 2002, 2003, 2007


C.

1001, 2002, 2003


D.

1001, 2002, 2002, 2003, 3001


Expert Solution
Questions # 35:

Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

Options:

A.

42.


B.

36.


C.

40.


D.

37.


Expert Solution
Questions # 36:

Which of the following project planning situations is the most frequent contributor to cost overruns?

Options:

A.

lack of detailed planning for operational start-up


B.

Insufficient planning for change management


C.

Inappropriate definition of work breakdown structure


D.

Inadequate definition of scope at the estimate (budget) stage


Expert Solution
Questions # 37:

What day would Activity C complete if the duration of Activity A was reduced by five days?

Options:

A.

35


B.

30


C.

45


D.

40


Expert Solution
Questions # 38:

Identify the late finish to develop plans and specs.

Question # 38

Options:

A.

9 months.


B.

10 months.


C.

8 months.


D.

7 months.


Expert Solution
Questions # 39:

The project team must communicate the project plan, goals and objectives to all stakeholders to ensure the stakeholders understand the plan, goals and objectives and then continue this communication throughout the project life Which statement below would stakeholders NOT be expected to contribute?

Options:

A.

Stakeholders review the basis the schedule after the schedule is developed


B.

Stakeholder communication should be the single most Important objective of a program of key cost and schedule performance indicators (KPls)


C.

Early in the planning process, a set of well-defined goals and objectives is reviewed by the stakeholders


D.

The key to successful acceptance by all stakeholders is a set of well-defined goals and objectives which should be Identified early in the planning process


Expert Solution
Questions # 40:

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

Question # 40

Options:

A.

450 lifts


B.

300 lifts


C.

45 lifts


D.

150 lifts


Expert Solution