Questions # 21:

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

Options:

A.

Negative float.


B.

Free float.


C.

Total float.


D.

Interfering float.


Expert Solution
Questions # 22:

If Activity E's duration changes to 4 months, what is the overall duration of the project.

Question # 22

Options:

A.

19 months.


B.

20 months.


C.

22 months.


D.

21 months.


Expert Solution
Questions # 23:

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Options:

A.

Non-excusable delay


B.

Compensable delay


C.

Non-compensable delay


D.

Excusable delay


Expert Solution
Questions # 24:

What does the narrow band at "Y" represent?

Question # 24

Options:

A.

Resource limitation period.


B.

A rework period.


C.

Activity inactivity.


D.

You cannot tell with the information supplied.


Expert Solution
Questions # 25:

If Activity A was delayed 5 days from starting, which of the following adjustments will NOT maintain the completion date of Activity C at Day 40?

Options:

A.

Reduce the duration of 'A' from 20 days to 10 days and replace the relationship from B' to 'C with FSO.


B.

Replace the relationship from 'B’ to 'C’ with SSO


C.

Reduce the duration of B" from 10 days to 5 days by compressing work effort


Expert Solution
Questions # 26:

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.

$289.000


B.

$321.000


C.

$193,000


D.

$327,000


Expert Solution
Questions # 27:

Which of the following statements is true?

Options:

A.

In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor


B.

In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor


C.

In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner


D.

In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor


Expert Solution
Questions # 28:

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

Options:

A.

15 days.


B.

0 days.


C.

5 days.


D.

10 days.


Expert Solution
Questions # 29:

Determine the driving activity for Activity 10001.

Question # 29

Options:

A.

Activity 11001.


B.

Activity 10002.


C.

Activity 9005.


D.

There is no driving activity for Activity 10001 in the backward pass.


Expert Solution
Questions # 30:

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.

Not suitable for complicated projects with multiple planned critical paths.


B.

Accuracy is increased by inserting delaying events into the as-planned schedule.


C.

Not suitable for projects with long durations.


D.

Less accurate as the analysis advances through the project.


Expert Solution