The cumulative cost baseline typically forms an "S" curve, reflecting slow initial expenditures, accelerating progress during peak activities, and tapering off as the project concludes.
Option A, B, and D do not represent the characteristic shape of a project's cost curve.
The PSP Study Guide highlights the "S" curve as a standard graphical representation of cumulative project costs over time.