Total float is the amount of time an activity can be delayed without affecting the project completion date.
Review the Network Diagram and Logic:
Activity F is not on the critical path, which allows for flexibility.
Analyzing the paths and slack in the diagram confirms that Activity F has the most total float.
Cross-Verification:
Option A: Incorrect. Activity I is on the critical path with no float.
Option B: Incorrect. Activity C is not the most flexible.
Option D: Incorrect. Activity D has limited slack.
Option C: Correct. Activity F has the maximum total float.